Auburn Grove – November 2017 Update

Please find below latest update from the developer for 28 Auburn Grove:

Auburn Grove – Newsletter November 2017

AuburnGrove_Nov 2017 1 AuburnGrove_Nov 2017 2 AuburnGrove_Nov 2017 3 AuburnGrove_Nov 2017 4 AuburnGrove_Nov 2017 5 AuburnGrove_Nov 2017 6

Read more

Auburn Grove – September 2017 Update

We wish to advise that construction at Auburn Grove is moving along smoothly! Rough-ins are now complete and the ground floor has been plastered. Windows are in and progress will continue for the month of October, with the arrival of kitchens and tiling around the same time.

The builder is still working towards handover in February.

Auburn Grove Sep 2017 1 Auburn Grove Sep 2017 2 Auburn Grove Sep 2017 3

Read more

Auburn Grove – August 2017 Update

A quick update for Auburn Grove! We have been advised that:

  • The tower crane has been dismantled
  • Internal framing almost completed
  • External scaffold installed to complete external walls
  • Internal plastering work has commenced
  • The roof has been completed.

 

AuburnGrove August 2017 1 AuburnGrove August 2017 2 AuburnGrove August 2017 3 AuburnGrove August 2017 4 AuburnGrove August 2017 5

Read more

Auburn Grove – July 2017 Update

Please find updates from the developer of 28 Auburn Grove, Hawthorn.

 All major concrete works have now been completed. Basement services are underway and internal walls are starting on ground floor next week. External works will then start in approximately 2 weeks time, with the crane currently scheduled to come down at the end of August, which will then enable us to install the lift.

If your contact details change at any point, please email customerservice@castrangilbert.com.au so that we can update your details in our system and ensure you receive future updates.

AuburnGrove_July 2017 2 AuburnGrove_July 2017 3 AuburnGrove_July 2017 4 AuburnGrove_July 2017 5 AuburnGrove_July 2017

 

Read more

Auburn Grove – April 2017 Update

Please find below the latest update for Auburn Grove!

–              The basement works have been completed including all piling, shotcrete walls and excavation.

–              Builders have poured half the slab on ground to the carpark and the entry ramp

–              Formation of the ground floor slab has commenced and aimed to pour prior to Easter

–              A tower crane is being erected on-site today.

–              Estimated completion is early 2018.

AuburnGrove_April2017 AuburnGrove_April2017_2

 

Read more

Auburn Grove – February 2017 Update

We wish to advise that there is an update for Auburn Grove! The builders have been working very hard and the construction is progressing well. The basement walls have just been recently put in the garage, with the floor due to be next. Once this is completed, the structure will appear very quickly over the next 2-3 months.

AuburnGrove_Feb2017

 

Read more

Auburn Grove – November 2016 Update

Lazzcorps has advised that site sheds are coming in next week for work to commence. The piling rig will be delivered and operations will commence prior to Christmas.

Read more

Auburn Grove – October 2016 Update

The Builders of Auburn Grove are due on site in the next 3 weeks.

Read more

Auburn Grove – July 2016 Update

Demolition of the site has now been completed, and Lazzcorps last project 8 Murphy Street is due for completion next month, opening the door for the foreman to bring his team over to Auburn Grove and commence building works.

Read more

Auburn Grove – June 2016 Update

Demolition is complete at Auburn Grove.

Construction is due to commence in the next 6 weeks as the team moves from Murphy Street to Auburn Grove.

 

Read more