Langtree – September 2017 Update

We wish to advise that the OC permits have been lodged and depending on councils, should be received within the next 2 weeks. Titles will be lodged shortly and once both the OC permits and titles are received, purchasers will be given 14 days’ notice of the exact settlement date. Your solicitor will be the best point of contact for settlements and any questions.

Purchaser Inspections

Defects and touch ups are currently in progress, with completion due for 13th October. Once completed you will be able to arrange your Purchaser Inspections, which will be held between Monday – Friday. The builders will contact you to book an appointment and will run off a first in best-dressed system. More details to follow.

Valuation Inspections

If you haven’t already, please organise your finance now. Valuation inspections can be booked in through your valuer. Please contact Emma at Citiwest on

Emma Petrzela <build@citiwestgroup.com.au>
M: (+61) 409 822 072
T: (03) 9336 2311
F: (03) 9336 1232

We will continue to provide further updates once we receive more information!

Read more

Langtree – September 2017 Update

We wish to advise that due to the recent weather conditions, 19 Langtree Avenue has been held up and is now expected to be completed at the end of September. Council inspections and surveyors occupancy inspection will occur over the new few weeks and once these are done, we will be in a better place to advise when Purchaser & Valuation Inspections can be booked. We will keep you updated as we receive more information.

Read more

Langtree – July 2017 Update

Please find below an update for 19 Langtree Avenue. We’ve been advised that:

  1. The carpet to townhouses 1-8 is due for completion on the 01/09. Touch ups will commence immediately after.
  2. The carpet to townhouses 9-16 is due for completion on the 25/08. Touch ups will commence immediately after.
  3. The driveway is due for completion on the 17/08.
  4. The landscaping is due for completion on the 01/09.
  5. Building surveyor inspection for occupancy is booked for 29/08.

The developer is still working on refining the dates for external works so the above timeframe may change. At this stage, settlement is expected for late September.

We will provide further updates as we receive them.

Read more

Langtree – July 2017 Update

The builders have advised that due to minor delays, 19 Langtree Avenue is now anticipated for completion in September.

The building is now approaching the final stages of construction with cabinetry installation having commenced and carpets have now been booked to be installed around mid to late August. Furthermore, the developer is currently acquiring all approvals from Council so that once the building is completed and the occupancy permit received, submissions can be made right away to the titles office, ready for settlement.

We will provide further updates, including photos, once we receive more details in the next few weeks.

 

Read more

Langtree – April 2017 Update

A quick update from the developer of 19 Langtree Avenue before the Easter period:

TH 1-8: Plaster commencing next week, approx. time frame 3 weeks (taking into account the Easter break).
TH 9-16: Tiler commencing next week, approx. time frame 3 weeks (taking into account the Easter break).

The builders are working towards a possible completion in June/July (which was incorrectly advised as May in our last update), subject to approvals from various bodies such as council and surveyors.

We will provide further updates after the Easter break. We wish you all a happy holiday period ahead!

Langtree_April_1 Langtree_April_2 Langtree_April_3 Langtree_April_4 Langtree_April_5 Langtree_April_6 Langtree_April_7 Langtree_April_8 Langtree_April_9

Read more

Langtree – March 2017 Update

We are happy to advise that the construction of 19 Langtree Avenue is expected to be completed in May. We will send out further details on inspections and settlement closer to the date.

 

Read more

Langtree – November 2016 Update

19 Langtree Avenue is progressing along well! The developer has advised that at this stage, construction is anticipated to be completed around April/May. However this can be subject to change as there is a 4 week Christmas closure period through the building industry. We will have a better understanding of when construction will be completed by the end of February/start of March.

Please note that this is in regards to construction only and does not reflect settlement date.

20161027_140123 20161027_140228 20161027_144740 20161027_140417 20161027_140815

Read more

Langtree – October 2016 Update

Townhouses 9 – 16 are still underway with cladding, roofing and rough-ins.

Townhouses 1 – 8 have just commenced first floor framing.

 

Read more

Langtree – September 2016 Update

Townhouses 9-16 have commenced plumbing and electrical rough ins, cladding and roofing have commenced and are due for completion over the next 3-4 weeks.

20160906_103413_resized

 

Read more

Langtree – July 2016 Update

1. Scaffolding is up on residences 9 – 16.

2. The second storey frames and trusses to residences 9 – 16 will be up over the next two weeks.

3. Plumber rough in to residences 9 – 16 to commence in approximately two weeks.

4. Roofing and cladding to residences 9 – 16 due to commence in approximately two weeks.

5. Steel works for residences 1 – 8 are due to start this week.

6. First floor framing for residences 1 – 8 are due to commence in approximately three weeks.

20160713_084212_resized

 

Read more