United Richmond – April 2017 Update

Please find below update from the developer of United Richmond:


United Richmond is progressing to programme thanks to the great work of Hamilton Marino Builders.

The piling is now complete, with excavation works well underway. As we progress through the excavation works, we will start erecting basement walls. By the end of May, we expect to complete the basement works with the pouring of the basement slab. Once the basement slab is completed, we can commence the structure.

The key dates are as follows:

Construction Commencement Date

Construction commenced October 2016.

Construction Programme

The key programme items are as follows:

 

  1. Site set up works         Completed
  2. Bulk excavation           Completed
  3. Basement works          In progress
  4. Structure works
  5. Services rough in
  6. Window glazing
  7. Facade cladding
  8. Internal fit out works
  9. Finishing works
  10. Practical completion

Settlement Date
Settlement is anticipated for early 2018.

We will keep you updated as we get closer to this date.
Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006
United Richmond April 1 United Richmond April 2 United Richmond April 3 United Richmond April 4 United Richmond April 5

Read more

United Richmond – January 2017 Update

We have received the following update from the developer for United Richmond.


United Richmond is progressing to programme thanks to the great work of Hamilton Marino Builders.

With site set up works well under way, piling is complete. Bulk excavation is underway. Throughout February the builder will continue to break through rock and dispose of excavated material which will enable commencement of shotcrete basement walls.

The key dates are as follows:

Construction Commencement Date

Construction commenced in October 2016.

Construction Programme

The key programme items are as follows:

Site set up works:        In Progress

Bulk excavation:           In Progress

Basement works:         In Progress

Structure works

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

 

Settlement Date
Settlement is anticipated for early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Below are updated construction photos.

We thank you for your cooperation.

United Richmond Jan17_A United Richmond Jan17_E United Richmond Jan17_D United Richmond Jan17_C United Richmond Jan17_B

Read more

United Richmond – November 2016 Update Part 2

Exciting news!

We are pleased to announce that construction has now commenced at United Richmond!

Please click below for the full details from the developer.

Click Here For More Details

Read more

United Richmond – November 2016 Update

The developer has advised that due to circumstances outside of their control, the construction management plan for United Richmond has taken longer than anticipated to be signed off from authorities. Unfortunately this has resulted in an unexpected delay in construction. We are hoping the issue will be resolved in the next week or two with construction expected to commence shortly after. We would like to apologise for the delay and any inconvenience this may have caused. We will keep you informed regularly once construction is underway.

For all matters in relation to settlement, please contact Jessica Hamra.
jhamra@blueearth.com.au
03 9347 6006

If your contact details change, please notify the developer at skoski@360propertygroup.com.au so that they may update the records accordingly.

Read more

United Richmond – June 2016 Update

In the space of only nine months we can proudly say that have sold out 95% of United Richmond.

Due to the success, we have been able to work with our preferred builder Hamilton Marino Builders to negotiate a building contract that ensures we deliver the project on time, on budget, to a level of quality that we are all proud of.

This will be our 17th collaboration with Hamilton Marino Builders. Recent works completed together include the following:

Northwood Apartments in Fitzroy North

A Apartments in Brunswick East

Mink Apartments in Essendon North

Moving forward, we will provide you with regular updates.

At this stage we are working closely with Hamilton Marino on the construction programme. This will include the formal start date and an estimated completion date,

Construction Commencement Date

Construction is expected to commence on 1 July 2016.

We will update you once it has formerly commenced.

 

Settlement Date Settlement is anticipated for late 2017.

We will keep you updated as we get closer to this date.

Contact Person Jessica Hamra will be your dedicated contact person for all matters in relation to updates.

Her details are as follows:

Name:  Jessica Hamra

Email:   jhamra@blueearth.com.au

Phone: 03 9347 6006

Once the builder is onsite we will update you with construction photos.

We thank you for your cooperation.