International – July 2017 Update

Please find below the latest updates from the developer for International:


International is continuing to progress to programme.

The structure is complete upto level 14. As we work our way up the structure we will commence the cladding. The cladding will incorporate the window systems, all feature architecture elements, wall finishing, and balustrading. As the apartments become watertight, we will commence the services rough in, with internal fit out works to follow.

In relation to the programme, the status is as follows:

 

Construction Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       In progress
  5. Services rough in                     In progress
  6. Window glazing                        In progress
  7. Facade cladding                       In progress
  8. Internal fit out works                In progress
  9. Finishing works
  10. Title registration
  11. Ready to settle

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for mid-2018.

We will keep you updated as we get closer to this date.
Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

We attach updated construction photos including the work in progress prototype kitchen.

We thank you for your cooperation.

The International July 1 The International July 2 The International July 3 The International July 4 The International July 5 The International July 7 The International July 8 The International July 9

Read more

The International – April 2017 Update

Please find below update from the developer of The International:


International is continuing to progress to programme.

Onsite, the project is progressing well with the structural works in motion. The tower crane is operational, enabling us to erect a full level of concrete panels every two weeks.

Externally, the structure has been complete up to level 9. Following the structure is the window systems, all feature architecture elements, wall finishing, and balustrading.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        In progress
  3. Basement works                      In progress
  4. Structure works
  5. Services rough in
  6. Window glazing
  7. Facade cladding
  8. Internal fit out works
  9. Finishing works
  10. Title registration
  11. Settlement

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006
The International April 1 The International April 2 The International April 3 The International April 4

 

Read more

The International – January 2017 Update

We have received the below updates from the developer of The International.


The International is progressing on programme thanks to the great work of Hamilton Marino.

We are currently working on the building structure, with piling works complete as of the end of last year. The tower crane has been erected, jump form installed, with the building core walls currently at level 5. The ground floor to level 2 slabs have now been poured, and it is anticipated that the level 3 slab will be poured by mid-February.

In relation to the construction programme the status is as follows:

Construction Programme

The key programme items are as follows:

Stage                                      Status

Site set up works:                    Completed

Bulk excavation:                       Completed

Basement works:                     Completed

Structure works:                      In Progress

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

Settlement Date
Settlement is anticipated for early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Below are updated construction photos.

We thank you for your cooperation.

The International Jan17_A The International Jan17_C The International Jan17_B

Read more

The International – November 2016 Update

The International is progressing to programme thanks to great work of Hamilton Marino Builders.

Bulk excavation works are now complete, with the crane currently being erected.

Construction Commencement Date

Construction commenced in July 2016.

Construction Programme

The key programme items are as follows:

   Stage                                             Status

Site set up works:                                Completed

Bulk excavation:                                 Completed

Basement works:                                 Completed

Structure works:                                      Commencing

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

Settlement Date
Settlement is anticipated for Early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi

Email:   kim@blueearth.com.au

Phone: 03 9347 6006

We attach updated construction photos.

international-photo-1 international-photo-2 international-photo-3 international-photo-4

Read more

The International – June 2016 Update

We are pleased to announce that Hamilton Marino Builders have been awarded the building contract for The International project.

Hamilton Marino are renowned as an industry leader in multi residential development.

This will be our 18th collaboration with them.  Recent works completed together include the following:

Northwood

A Apartments

Mink

Construction has commenced with an estimated settlement date of first quarter of 2018. Construction Programme The key programme items are as follows:

Site set up works

Bulk excavation

Basement works

Structure works

Service rough in

Window and façade glazing

Internal fit out works