Fitz & Co – June 2017 Update

We are happy to advise that construction for Fitz & Co is progressing along nicely. The retention system, basement drainage, basement slab and its core walls and columns, and ground floor slab have all been completed. The tower crane is currently being installed and works are commencing on the townhouses and precast from ground to 1st floor.

We will provide you with further updates as the project progresses.

FC_June_1 FC_June_2 FC_June_3

Read more

Fitz & Co – February 2017 Update

We have been provided the following updates for Fitz & Co.

Site progress:

Bored piers installation completed
Excavation process will be completed this week
Capping beams are  now completed
Shotcrete to bored piers will be completed next week
Strip and Pad Footing poured to townhouse area
Precast panel erection will start to townhouse next week

The anticipated completion date is February 2018

FC_Feb_2017_1

FC_Feb_2017_2

FC_Feb_2017_3

Read more

Fitz & Co – December 2016 Update

We have been advised that anticipated completion date for Fitz & Co is February 2018.

Site progress:

Bored piers installation will be complete by the 22nd December 2016
Excavation process started on the east elevation of the site
Capping beam at the east elevation is now completed
Capping beams to be completed by the 23rd of December 2016

fc_dec_2016_4 fc_dec_2016_3 fc_dec_2016_2 fc_dec_2016_1 fc_dec_2016

Read more