Rima – December 2017 Update

Please find below update from the developer for Rima:


Rima is continuing to progress to programme.

We have completed the basement works, and are working our way up the structure. As we work our way up the structure we commence the cladding. The cladding will incorporate the window systems, all feature architecture elements, wall finishing, and balustrading. As the apartments become watertight, we will commence the services rough in, with internal fit out works to follow.

In relation to the programme, the status is as follows:

Construction Programme

The key programme items are as follows:

 

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       In progress
  5. Services rough in                     In progress
  6. Window glazing                        In progress
  7. Facade cladding                       In progress
  8. Internal fit out works
  9. Finishing works
  10. Title registration
  11. Occupancy permit
  12. Ready to settle

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for June 2018.

We will keep you updated as we get closer to this date.
Contact Person

Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Rima Photo 1 Rima Photo 2 Rima Photo 3 Rima Photo 4

Read more

Rima – July 2017 Update

Please find below latest update from the developer of Rima:


Rima is continuing to progress to programme.

We have completed the basement retention works, with the commencement of the basement slab structure shortly. We will start from the bottom of the third basement, and work our way up the structure until we pour the ground floor slab. The programme shows the ground floor slab will be poured in late August 2017. Upon completion of the ground floor slab, we can commence the structure work.

In relation to the programme, the status is as follows:

Construction Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works
  5. Services rough in
  6. Window glazing
  7. Facade cladding
  8. Internal fit out works
  9. Finishing works
  10. Title registration
  11. Ready to settle

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for mid-2018.

We will keep you updated as we get closer to this date.
Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006
We attach updated construction photos.

We thank you for your cooperation.

Rima July 1 Rima July 2 Rima July 3 Rima July 4

Read more

Rima – April 2017 Update

Please find below update from the developer of Rima:


Rima is continuing to progress to programme.

The piling is now complete, with excavation works well underway. As we progress through the excavation works, we will continue erecting basement walls. By the end of May, we expect to complete the three level basement. Once the basement slab is poured, we can commence the structure.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

 

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                       In progress
  3. Basement works                      In progress
  4. Structure works
  5. Services rough in
  6. Window glazing
  7. Facade cladding
  8. Internal fit out works
  9. Finishing works
  10. Title registration
  11. Settlement

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for mid-2018.

We will keep you updated as we get closer to this date.
Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:  kim@blueearth.com.au
Phone: 03 9347 6006
Rima April 1 Rima April 2 Rima April 3 Rima April 4

Read more

Rima – January 2017 Update

We have received the below updates from the developer of Rima.


Rima is progressing to programme thanks to the great work of Orange Building Solutions.

We are currently working on the basement retention works, with retention piling completed as of the start of this week. Capping beam works and stage 1 bulk excavation works will be commencing as of next week. It is anticipated that the bulk excavation of all 3 levels of the basement will be completed by the start of April.

The key dates are as follows:

Construction Commencement Date

Construction commenced on 1 December 2016.

Construction Programme

The key programme items are as follows:

Site set up works:        Completed

Bulk excavation:           In Progress

Basement works:         In Progress

Structure works

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

 

Settlement Date
Settlement is anticipated for early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Below are updated construction photos.

We thank you for your cooperation.

Rima Jan17_A Rima Jan17_E Rima Jan17_D Rima Jan17_C Rima Jan17_B

Read more

Rima – December 2016 Update

We have received the below updates from the developer of Rima.


We are pleased to announce with the Rima nearly sold out we have been able negotiate a commencement date with the builder Hamilton Marino Builders.

The key dates are as follows:

Construction Commencement Date

Construction commencing on 1 December 2016.

Construction Programme

The key programme items are as follows:

Site set up works

Bulk excavation

Basement works

Structure works

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

 

Settlement Date
Settlement is anticipated early 2018.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Read more