Sable Verde – August 2017 Update

Please find below updates from the developer for Sable Verde:


Works are progressing well through the winter months with the basement concrete slab floor poured and the precast panel walls, lift shaft and stairwell in place. Currently, works are continuing well with the pouring the ground floor concrete slab.
With the weather improving and the basement structure completed, works are programmed to complete the structure in the coming months…

Aug2017Update

Read more

Sable Verde – June 2017 Update

1

Excavation and basement works are underway at Sable Verde. All going along to schedule.

Read more

Sable Verde – April 2017 Update

We are happy to advise that built excavation for the Sable Verde development is well on the way and Shotcreting to piles is moving along nicely.

SableVerde_April1 SableVerde_April2

Read more

Sable Verde – March 2017 Update

Construction Progress

We are happy to advise that all piling is complete and ahead of schedule as at 25/03/17.

Works are continuing as to program and barring inclement weather we look forward to a continuous Winter build.

SableVerde_March1SableVerde_March2

Read more

Sable Verde – February 2017 Update

We are pleased to announce that construction works have now commenced at Sable Verde! We will continue to provide you with regular updates, including photos, as the construction progresses.

Please click here for a video of the construction site.

 

 

 

 

 

Read more