Mabel – November 2017 Update

Mabel Apartments are progressing well and looking great!  First-floor slab is currently being poured. More updates to follow.

Mabel nov 2017 1 Mabel nov 2017 2

Read more

Mabel – September 2017

We are pleased to announce that progress is running swiftly at Mabel Mordialloc, with builders scheduled to pour the Ground floor transfer deck this Wednesday. We will continue to keep you updated as the development progresses.

Mabel September 2017

Read more

Mabel – July 2017 Update

We are pleased to advise Mabel Mordialloc is now demolished and underway. Piling and Excavation is complete on the basement and walls are currently being sprayed. Ground floor slab is around 4-5 weeks away. Completion looking like April/May depending on weather.

Mabel July 2017

Read more

Mabel – May 2017 Update

We are happy to advise that demolition for Mabel Mordialloc has been completed and the builders should be on site within 2 weeks. As construction progresses, we will provide you with further updates on the project including photos of the development.