Curve – March 2018 Update

We wish to advise that works are underway at Curve – 294 Keilor Road, Essendon North! The stage 1 building permit has been issued (for construction of basement retention system) and power line relocation works have been completed. The building contractor is currently levelling the site and creating a hardstand area for the piling rig so that piling works can commence within the next two weeks.

We will continue to provide further updates as construction progresses at Curve!

Read more

Curve – February 2018 Update

We wish to advise that there is a delay to Curve, as the builders were not able to be on site early this month (February) as previously advised. This was dependent on council approving the site management plan which the developer has yet to receive. However, they hope to receive this any day now and thus expect to see builders on site by March 5th.

We apologise on behalf of the developer for this delay and will provide further updates in March.


Read more

Curve – January 2018 Update

We wish to advise that the power lines have now been placed underground. This clears the way for the builders to start upon their return from holidays in early February. We will provide further updates when construction commences in the next month.



Read more

Curve – October 2017 Update

We are happy to advise that Project Group ( has been appointed to build the project with construction due to commence shortly after Christmas.

In regards to the power work, initially, it was thought that the power lines could go underground under the footpath (so that it is not blocking construction, as well as not obstructing the aesthetic values of the apartments). However, they were unable to move forward with this due to the presence of pipes under the footpath. Thus, as a result, the development team is now planning for the power lines be placed under the road instead. It is expected that this will be achieved in the next 4 – 6 weeks. We will keep all purchasers updated on progress as we receive more information.


Read more

Curve – September 2017 Update

We wish to advise that we have received an update for the Curve development in Essendon North. The developer advised that the target commencement date for the project is November 2017, once the undergrounding works for the high voltage and low voltage power lines have been completed by Jemena.

We would like to apologise on behalf of the developer for the construction commencement delays thus far as a result of the delay with works by Jemena. We will continue to provide further updates once we receive more information.

Read more

Curve – June 2017 Update

Great news! The developer for Curve has advised that paperwork with the designated builders are now being finalised.
The team is waiting on the electrical company, Jemena Electricity, to provide the power station on site and once delivered, construction will be able to commence in the next month or so.
We will provide you with further updates when construction commences!

Read more