Chester – February 2018 Update

The Developer for 3 Chesterville Rd has advised that they are currently in the process of completing the appointment of a builder, and are finalising all documentation for structural and design works. This will save a considerable amount of time once the builder will be ready to commence construction.

At this stage they envisage that the commencement of construction will most likely occur second half of 2018. Once construction commences we anticipate that the construction period will be based on approximately 14 months. We will continue to update you as construction progresses.

Read more

Chester – November 2017 Update

We have been advised by the developer that “Chester” at 3 Chesterville, Cheltenham is scheduled to commence demolition in January 2018. The team is currently working through the design and once demolition commences, the project is on track for completion in the second quarter of 2019.

We will continue to provide you with further updates as we receive more information.