Bayside Tower – Complete & Settled

Bayside Tower is now complete & settled!

station_407_6_moorabin_facade_low_res

Read more

Bayside Tower – October 2015 Update

Please be advised that Titles were received yesterday, 21/10/2015 for Bayside Tower.

A letter has been issued to all Purchaser’s Solicitors advising of this.

An inspection is scheduled with the MFB for their certification of the building for tomorrow, 23/10/2015. 

As soon as MFB sign off is issued the certificate of occupancy will be issued.

A letter will go out to all Purchaser’s Solicitors as soon as the Certificate of Occupancy is received.

 

Read more

Bayside Tower – Blinds Offer

Blinds Offer – Bayside Tower

These quotes are ONLY to be used as a guide as the apartments may slightly differ – each and every apartment MUST be measured and quoted before any orders can be placed.

Below are the apartment numbers that each quote (TYPE) relates to.

D – 1.04, 2.04, 3.04, 4.04

E – 1.05, 2.05, 3.05, 4.05

F – 1.06, 2.06, 3.06, 4.06

G – 1.07, 2.07, 3.07, 4.07, 5.06, 6.06, 7.06, 8.06, 9.06

H – 1.08, 2.08, 3.08, 4.08, 5.07, 6.07, 7.07

K – 1.11, 2.11, 3.11, 4.11, 5.10, 6.10, 7.10

L – 1.12, 2.12, 3.12, 4.12, 5.11, 6.11, 7.11

M – 1.13, 2.13, 3.13, 4.13, 5.12, 6.12, 7.12, 8.10, 9.10, 1.14, 2.14, 3.14, 4.14, 5.13, 6.13, 7.13, 8.09, 9.09

O – 1.15, 2.15, 3.15, 4.15, 5.14, 6.14, 7.14, 8.11, 9.11

P – 1.01, 2.01, 3.01, 4.01, 5.01, 6.01, 7.01, 8.01, 9.01

R – 1.02, 2.02, 3.02, 4.02, 5.02, 6.02, 7.02, 8.02, 9.02, 1.03, 2.03, 3.03, 4.03, 5.03, 6.03, 7.03, 8.03, 9.03

S – 5.04, 6.04, 7.04, 8.04, 9.04

T – 5.05, 6.05, 7.05, 8.05, 9.05

W – 1.09, 2.09, 3.09, 4.09, 5.08, 6.08, 7.08

X – 1.10, 2.10, 3.10, 4.10, 5.09, 6.09, 7.09

 

Click here to view quotes

 

Contact George directly – 8.07, 9.07, 8.08, 9.08

If you have any questions, please contact:

 

George Poulios

M: 0408 700 527

E: george@rollingblinds.com.au

 

Kind regards,

Castran Gilbert

Read more

Bayside Tower – September 2015 Update PART 2

CG_6_STATION_ST_1793CG_6_STATION_ST_1776CG_6_STATION_ST_1771CG_6_STATION_ST_1737CG_6_STATION_ST_1746CG_6_STATION_ST_1761

Sneak preview of a completed apartment at Bayside Tower – Not long now!

Read more

Bayside Tower – September 2015 Update

ALMOST COMPLETED!

BOOK IN YOUR INSPECTION TIME NOW…

M13 16_8000_15 09 09_Purchaser Letter_Pre-Settlement Inpsection- Bayside..._Page_1M13 16_8000_15 09 09_Purchaser Letter_Pre-Settlement Inpsection- Bayside..._Page_22FullSizeRender1FullSizeRender3FullSizeRender

Read more

Bayside Tower – August 2015 Update

Dear Clients and Associates of Bayside Tower Apartments,

We write to provide an update of progress on construction of your apartment at 4-6 Station Street, Moorabin. The project is nearing completion and we want to inform you that construction is progressing ahead of schedule; the current target is an early November financial settlement.

The `Certificate of Occupancy’ forecast to be in mid October.

The EXCITEMENT has now commenced!

  • You should have started your loan process already.
  •  Your financier will need to send out a valuer for valuation and your sales agent will be the contact person for all valuation inspections. Valuation inspections will be available
    • Level 1-4 from Monday 21st September to Friday 25th of September 2015.
    • Level 5-9 from Tuesday 29th September to Saturday 3rd of October 2015.
    • Bookings can be made by contacting Phil King from Urban.
  • Council certified plan of subdivision for titles registration is expected in early September and council has now assigned the property address ‘6 Station Street’ for Bayside Tower Apartments.
  • We expect to obtain the `Certificate of Occupancy’ mid October 2015.
  • Pre-Settlement inspections will be held in the two weeks between late September and early October, We will be in contact with more detailed time slots for the purchaser pre-settlement inspections in the coming weeks.
  • In accordance with the sales contract financial settlement should occur 14 days after issuance of Certificate of Occupancy and Title Registration.
  • At financial settlement you will be provided a Settlement Pack containing your apartment keys, remotes, warranty documents, manuals, emergency contact numbers, resident house rules, etc…..
  • If you are renting out your apartment, your property manager can only access the apartment after you have settled.
  • No one is to go onsite before financial settlement outside of the pre-arranged defect inspection.

 

Our solicitor Tisher Liner FC will send out correspondence to your solicitor as soon as we received titles registration and certificate of occupancy.

Urban Contact: Phil King via phone 0408 525 406 or email phil.king@urbandevelop.com.au

Our solicitor and I will continue communicating to you over the following weeks working towards a smooth settlement.

Regards,

Phil King
Urban

Read more

Bayside Tower – July 2015 Update

We write to provide an update of progress on construction of your apartment at Bayside Tower, 4-6 Station Street, Moorabbin. The project is nearing completion and we want to inform you that construction is progressing ahead of schedule; the current target is an early to mid October 2015 financial settlement

The `Certificate of Occupancy’ forecast to be in October 2015.

The builder has now have achieved the following:

 

  • Concrete Structure is compete & tower crane to be removed
  • Glazing is complete to level 6
  • Wall framing is complete up to level 7
  • Permanent electricity has been to be connected.
  • Water tapping has been connected
  • Storm Water has been connected
  • Lift fit out is under way

 

We suggest you contact your financier to prepare for October 2015 settlement.  Your financer will appoint a valuer to complete a valuation of your apartment and they will need access to the building and your apartment to complete this valuation. We will confirm a number of dates and provide these to your sales agents and legal representatives. Plesase note we will not be letting valuers through until September/October 2015. To assist valuers with scheduling access to the building please arrange for them to contact Phil King at Urban on 0408 525 406 to co-ordinate an inspection time. Urban will also be in touch to schedule purchaser pre-settlement inspections in due course.

Buyers will ONLY be allowed onsite once we have achieved Certificate of Occupancy and a pre-settlement inspection date is booked before settlement. We will contact you towards completion to let you know when this date will be.

We thank you for your co-operation in the above to allow a successful completion and settlement process.

Read more

Bayside Tower – May 2015 Update

BaysideTower

Read more

Bayside Tower – February 2015 Update

IMG_6621 IMG_6627

Great news for Bayside purchasers! Construction is running ahead of schedule,
with completion and settlement expected for December 2015.

We have been informed builders have completed basement slab.
Level one slab is 50% completed with level 2 frame work already started.

Read more

Bayside Tower – November 2014 Update

 

Bayside_NOV3Bayside_NOV2

We have been informed the basement excavation is now complete, crane assembled is on site and ground bearing slabs are currently being poured.

Completion is due early 2016, we will keep you informed with further updates in the New Year.

Read more