Gardiner Rise – Complete!

high_310_35_43_glen_iris_facade_1 high_310_35_43_glen_iris_kitchen_low_res high_310_35_43_glen_iris_living_low_res high_310_35_43_glen_iris_bathroom_low_res high_310_35_43_glen_iris_bedroom_low_reshigh_310_35_43_glen_iris_balcony_low_res

Read more

Gardiner Rise – Final Inspections

We are pleased to inform you that your apartment at 35 – 43 High Street, Glen Iris is ready for final inspection.

The inspections will take place Monday 22nd August to Friday 26th August between 8:00am- 4:00pm. Click Here to book your inspection online.

Please note that appointments need to be booked by Thursday the 18th of August and inspections will be limited to 15 minutes. A representative from Figurehead will guide you through the inspection. For your safety, only 4 people maximum can be taken through an inspection at any time. Please also refrain from roaming the site on your own and wait for the representative from Figurehead to accompany you instead.

If you have any questions, please don’t hesitate to contact Rachel Sleeman on 0427 545 493.

Read more

Gardiner Rise – July 2016 Update

Gardiner Rise is on track for completion towards the end of August, now is the time to start making finance arrangements.

We’ve partnered with Neue Black to arrange your finance. Neue Black are finance brokers that specialise assisting people to arrange finance when purchasing property off the plan.

They have extensive market knowledge and great relationships with a wide range of lenders and will provide you with the most competitive options.

They were just voted as Finance Broker of Year at the Australian Broking Awards so we think you’ll find the experience at Neue Black to be first class.

If you require any assistance with finance, please contact Marshall Condon on;

MOBILE – 0476 823 167

OFFICE – 03 9826 2555

EMAIL – marshall@neueblack.com.au

Read more

Gardiner Rise – Valuation Inspections

We are pleased to announce the following date for inspections;

VALUATIONS: Monday July 18th

PLEASE NOTE: Times must be arranged prior to this by contacting Mitch Waters, the Site Project Manager on;

Mobile: 0406 364 972

Email: mitchell.waters@figurehead.com.au

PURCHASER FINAL INSPECTIONS: To be confirmed (approximately early August).

Read more

Gardiner Rise – June 2016 Update

ExtractPage1_Page_1 ExtractPage1_Page_2

Read more

Gardiner Rise – May 2016 Update

The construction of Gardiner Rise Apartments is tracking well ahead of program.

The plastering is almost complete, joinery is being installed to Level 4 and tiling currently on Level 3.

External treatments are progressing well with the scaffold due to come down at the end of May.

April Pics_Page_1 April Pics_Page_2 April Pics_Page_3

Read more

Gardiner Rise – February 2016 Update

We are pleased to announce that the completion date for Gardiner Rise is set for approximately the 19th of August, 2016.

Read more

Gardiner Rise – December 2015 Update

2015-11-28 07.08.48

Read more

Gardiner Rise – September 2015 Update

GARDINER RISEimage2 GARDINER RISEimage3 GARDINER RISEimage6Figurehead Construction advises that the structure is scheduled to be complete by late July 2016.

Read more

Gardiner Rise – May 2015 Update (Part 2)

Figurehead Construction advises that the structure is scheduled to be complete by late July 2016.

  • Piling and capping beam works have commenced
  • Excavation/ retention will commence late May 2015 and be completed in August 2015
  • In ground services works will take approximately 2 weeks, starting end July
  • Vertical structure works are due to commence in August 2015
  • Internal fit-out is due to commence in November 2015, with estimated completion in September 2016

Project completion date is estimated to be October 2016. More updates to come.