Eight Murphy – Complete!

murphy_8_south_yarra_facade_low_res murphy_102_8_south_yarra_kitchen_low_res murphy_103_8_south_yarra_living_low_res murphy_306_8_south_yarra_balcony_low_res murphy_306_8_south_yarra_bathroom_low_res

Read more

Eight Murphy – Final Inspections

Great news! Lazzcorp has advised that the Certificate of Occupancy should be issued by early next week and the Titles from the titles office by late next week. This will then enables the developer to trigger the settlement process.

Final Inspections

As of Monday the 29th of August, ground to level 3 inclusive will be ready for you to conduct a final inspection. The penthouses are running about 1 week behind so we will contact the 4 penthouses buyers again shortly.

Please call Tim Brown on 0417 766 778 to arrange a time to inspect your unit.

If you have any queries, please don’t hesitate to contact Tim by phone or email at tbrown@castrangilbert.com.au

Read more

Eight Murphy – August 2016 Update Part 2

Progress on site is continuing very quickly we hope on Monday to be able to confirm a date for the final inspections and the Developer is working towards being able to settle the apartments in the middle of September.

If you haven’t already done so, please speak with your Financier and have them arrange the Valuation with myself, Tim Brown 0417 766 778, as soon as possible.

 

Read more

Eight Murphy – August 2016 Update

Lazzcorp have advised that EIGHT MURPHY will be ready for Valuer inspections as of Monday the 15th of August.

If you are intending to take a loan out for the purchase, please have your Valuer contact Tim Brown on 0417 766 778 or tbrown@castrangilbert.com.au to arrange an inspection for after the 15th of August.

Please note the building will not be ready for purchaser inspections at that time, however we are expecting Levels 1 – 3 inclusive to be ready approximately one week later and for the ground and top floor to be ready in early September.

We will contact you when we have more definitive dates for your inspections.

 

Read more

Eight Murphy – July 2016 Update Part 2

Eight Murphy continues to take shape and the final details have slowed progress as it requires a lot of attention to detail.

The building looks fantastic, we expect to invite Valuers down in late August for Levels 1 – 3 and early September for the 4 penthouses.

Final inspections are expected in the first two weeks of September and all settlements in approximately mid to late September.

Read more

Eight Murphy – July 2016 Update

 

Eight Murphy is progressing along strongly but the attention to detail that this bespoke development deserves is taking a little longer than first anticipated.

The building looks amazing and the attention to detail looks exactly what you would expect.

We hope to be in a position to invite Valuers down in a couple of weeks, we expect final inspections to be in late July or early August and Settlement now looks likely to be late August, or early September.

Keep warm and we will contact you again shortly.

IMG_4173IMG_4169IMG_4171 IMG_4170

 

Read more

Eight Murphy – May 2016 Update

LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_1 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_2 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_3 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_4 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_5 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_6 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_7 LAZZCORP NEWSLETTER - APRIL 2016[1]_Page_8

Read more

Eight Murphy – April 2016 Update

Whilst you have hopefully been away with the kids during the school holidays Lazzcorp have been hard at work on site.

Construction continues to forge on, meeting all deadlines.

We are still on track for completion in approximately July.

We are awaiting confirmation of a package that the Developers have been putting together for the supply of blinds, washing machines and dryers as well as fridges, we hope to have this in the next few weeks to be able to send it to each buyer for their consideration.

Stay tuned.

IMG_3774

 

Read more

Eight Murphy – March 2016 Update

We are still working towards a late July settlement.

LAZ_8_MURPHY_1846 LAZ_8_MURPHY_1834 LAZ_8_MURPHY_1831 LAZ_8_MURPHY_1829 LAZ_8_MURPHY_1780 LAZ_8_MURPHY_1767 LAZ_8_MURPHY_1763 LAZ_8_MURPHY_1757 LAZ_8_MURPHY_1740 LAZ_8_MURPHY_1733 LAZ_8_MURPHY_1718 LAZ_8_MURPHY_1699 LAZ_8_MURPHY_1697 LAZ_8_MURPHY_1695

Read more

Eight Murphy – February 2016 Update

Since returning from Christmas the site has been extremely busy, works continue inside with plumbing and wiring and now the appearance of plasterboard to most walls and even the cabinetry is starting to arrive on site.

True to its word Lazzcorp continue to work to a schedule that will see completion of works in approximately June and settlement most likely in late July.

IMG_3672 IMG_3673 IMG_3674

 

Read more