Ruba – Complete & Settled

camberwell_go2_565_camberwell_facade_low_res

Read more

Ruba – September 2015 Update

Completion is now expected approximately late September / early October.

Read more

Ruba – 22nd May 2015 Update

Hamilton Marino have advised they are running ahead of schedule in relation to the completion of our Ruba development.

Please prepare for settlement, end of August 2015

Details will be sent closer to completion, in relation to the pre-settlement inspection process and contacts.

 

Read more

Ruba – 11th May 2015 Update

Ruba 8 May 2015 _Page_1 Ruba 8 May 2015 _Page_2 Ruba 8 May 2015 _Page_3 Ruba 8 May 2015 _Page_4

The structure is now complete.

 

Read more

Ruba – May 2015 Update

Ruba Construction Photos 16 March 2015 _Page_2 Ruba Construction Photos 16 March 2015 _Page_3 Ruba Construction Photos 16 March 2015 _Page_4 Ruba Construction Photos 16 March 2015 _Page_5

SOLD OUT! 

Construction progressing well. Complete due approximately September 2015.

Basement levels stripped of formwork

Ground floor level floor slab completed

Level one slab formed and been poured

Side adjoining owners boundary fence under construction

Everything is running to schedule with completion estimated November 2015

Read more