Roseville – November 2016 Update

 

We have been advised that settlement is expected to occur within the next 2-3 weeks.

Please ensure that you have your finance in order in preparation for settlement.

Unfortunately we have not been provided with a clear settlement date yet as the project is still with the Titles Office. We have been advised that the Titles Office is implementing a new digital system which has added to the backlog of matters to be processed.

We will keep you informed as we are advised of progress.

Read more

Roseville – August 2016 Update

We are pleased to announce that both the Occupational Permit and Practical Completion were achieved yesterday at Roseville.

 

Read more

Roseville – July 2016 Update

The Builders have advised that they are 2 – 3 weeks away from Practical Completion.

Titles will be in by approximately early August or end July.

Read more

Roseville – June 2016 Update

The building is looking fantastic at Roseville Apartments.

Not long to go now!

2 3 4 5

Read more

Roseville – April 2016 Update

IMG_6376FullSizeRenderF1ullSizeRenderIMG_6373 IMG_6371 IMG_6367 IMG_6366

Read more

Roseville – February 2016 Update

The structure is complete.

Framing works for Wall Partition is currently at level 3 and 4.

Aluminium Window frames are in progress.

Services rough ins are in level 3 and 4.

Completion is still on schedule for approximately August 2016.

Image_Page_1 Image_Page_2 Image_Page_3 Image_Page_4 Image_Page_5 Image_Page_6 Image_Page_7 Image_Page_8 Image_Page_9

Read more

Roseville – September 2015 Update

IMG_0875IMG_0823 IMG_0822 IMG_0821 IMG_0819IMG_0872IMG_0874IMG_0540

Read more

Roseville – July 2015 Update

DSCN2096 DSCN2095 DSCN2077

Leake_IMG_0540Excavation works are well underway!

Read more

Roseville – May 2015 Update

Construction is progressing well – completion May 2016

20.-Leake-Demo- 10.-Leake-Demojpg