Gordon Parade – June 2017 Update

We are happy to advise that we have received an update from the developer for Gordon Parade. All internal fixtures, fittings and paintings have now been finished. The builders are currently working on external surfaces and driveways, which is estimated to be completed by the end of the month. Once this is done, they will move onto landscaping.

The project is currently scheduled for building completion in mid-July and we will provide further updates when it is completed.

Read more

20 Gordon parade – February 2017 Update Part 2

We wish to advise that 20 Gordon Parade is almost at completion. Most of the work is nearly done with only the following items left to be completed:

Appliances installation
Balustrades
Gas pipe installation
Connection of gas metres
Sewer works.

The developer expects to receive occupancy permits from the second week of March, with settlement expected for Late March.

Gordon_Feb2017_7 Gordon_Feb2017_6 Gordon_Feb2017_5 Gordon_Feb2017_4 Gordon_Feb2017_3 Gordon_Feb2017_2 Gordon_Feb2017_1

Read more

20 Gordon Parade – February 2017 Update

We have been advised that 20 Gordon Parade is now providing valuation inspections from the week commencing 20th February. Please contact Jason Wong from Vita Built on 0497 012 473 to book your inspections.

Jason Wong
Vita Built
0497 012 473

We will contact you again shortly with further information on purchaser inspections & settlement.

 

Read more

20 Gordon Parade – January 2017 Update

We have been advised by the developers that unfortunately the settlement of 20 Gordon Parade has been delayed until the end of February. This is due to utilities providers being slow to install utilities infrastructure as well as delays from Council on the approval of these infrastructure requests.

Settlement is now expected for the end of February with Valuation Inspections to start beginning of February.

On behalf of the developer, we would like to apologise for the inconvenience caused by this delay. We will contact all purchasers with further details on inspections when these are arranged.

 

Read more

20 Gordon Parade – November 2016 Update

We are pleased to confirm that settlements for 20 Gordon Parade, Yarraville, will commence on the week commencing Monday, the 16th of January

Read more

20 Gordon Parade – October 2016 Update

The project is at lock-up stage.

Internal plastering has begun and will be followed by tiling and bathrooms.

Aiming for approximately mid-December Settlements, pending weather. 

img_3002img_2997

 

Read more

20 Gordon Parade – September 2016 Update

Lock-up targeting the 1st of October.

Aiming for competition in approximately mid December.

img_2811 img_2810 img_2809 img_2808

Read more

20 Gordon Parade – August 2016 Update

Roofing should be completed this week. Windows and doors installed next week. Lock-up will be completed within the next 2-3 weeks. Then joinery will follow. 

IMG_9281 IMG_9282 IMG_9283

 

Read more

20 Gordon Parade – July 2016 Update

The ground floor and first floor framing stages are complete.

Roofing members are expected to be installed by the end of this week.

Lock-up stage (installation of all external doors, windows and cladding) should be completed in the next three weeks.

IMG_7958 IMG_7957 IMG_7956 IMG_7955

Read more

20 Gordon Parade – May 2016 Update

1

Read more
Next Page »