Gordon Parade – September 2017 Update

We have been advised by the developer for 20 Gordon Parade that there were delays to the project due to delays in finalising the services connections. There were issues with incorrect installation of plumbing works so the plumber had to rectify this and the utility provider had to come on-site to check this again. The developer advised today that:

Services have been completed and soil has been backfilled over the infrastructure. An inspection of the site is happening on Tuesday and metres from the providers will he ordered next week. It should take a couple of weeks for metres to arrive, in which time the boardwalk and driveway will be completed. We are hoping for the [plan of subdivision] to be submitted by end of the month“.

The developer apologises to all purchasers for the delays.

We will continue to follow up with the developer but if you have any concerns or questions, you can also contact your solicitor who’d be able to discuss in further details with the vendor’s solicitor.

Read more

Gordon Parade – July 2017 Update

We wish to advise that we have received an update from the developer of 20 Gordon Parade. He advised that delays were due to issues with connecting the services to the mains, which has now been resolved. Builders are currently finishing off the driveway and they are aiming to have the plan of sub-division registered by end 1st week August, after which, they will be in a position to do final inspections mid-August and settlement in late August/ early September.

Read more

Gordon Parade – June 2017 Update

We are happy to advise that we have received an update from the developer for Gordon Parade. All internal fixtures, fittings and paintings have now been finished. The builders are currently working on external surfaces and driveways, which is estimated to be completed by the end of the month. Once this is done, they will move onto landscaping.

The project is currently scheduled for building completion in mid-July and we will provide further updates when it is completed.

Read more

20 Gordon parade – February 2017 Update Part 2

We wish to advise that 20 Gordon Parade is almost at completion. Most of the work is nearly done with only the following items left to be completed:

Appliances installation
Balustrades
Gas pipe installation
Connection of gas metres
Sewer works.

The developer expects to receive occupancy permits from the second week of March, with settlement expected for Late March.

Gordon_Feb2017_7 Gordon_Feb2017_6 Gordon_Feb2017_5 Gordon_Feb2017_4 Gordon_Feb2017_3 Gordon_Feb2017_2 Gordon_Feb2017_1

Read more

20 Gordon Parade – February 2017 Update

We have been advised that 20 Gordon Parade is now providing valuation inspections from the week commencing 20th February. Please contact Jason Wong from Vita Built on 0497 012 473 to book your inspections.

Jason Wong
Vita Built
0497 012 473

We will contact you again shortly with further information on purchaser inspections & settlement.

 

Read more

20 Gordon Parade – January 2017 Update

We have been advised by the developers that unfortunately the settlement of 20 Gordon Parade has been delayed until the end of February. This is due to utilities providers being slow to install utilities infrastructure as well as delays from Council on the approval of these infrastructure requests.

Settlement is now expected for the end of February with Valuation Inspections to start beginning of February.

On behalf of the developer, we would like to apologise for the inconvenience caused by this delay. We will contact all purchasers with further details on inspections when these are arranged.

 

Read more

20 Gordon Parade – November 2016 Update

We are pleased to confirm that settlements for 20 Gordon Parade, Yarraville, will commence on the week commencing Monday, the 16th of January

Read more

20 Gordon Parade – October 2016 Update

The project is at lock-up stage.

Internal plastering has begun and will be followed by tiling and bathrooms.

Aiming for approximately mid-December Settlements, pending weather. 

img_3002img_2997

 

Read more

20 Gordon Parade – September 2016 Update

Lock-up targeting the 1st of October.

Aiming for competition in approximately mid December.

img_2811 img_2810 img_2809 img_2808

Read more

20 Gordon Parade – August 2016 Update

Roofing should be completed this week. Windows and doors installed next week. Lock-up will be completed within the next 2-3 weeks. Then joinery will follow. 

IMG_9281 IMG_9282 IMG_9283

 

Read more
Next Page »