Salisbury – June 2017 Update

We have been advised that due to delays caused by environmental issues, the project is now scheduled for completion in mid July.

Read more

Salisbury – February 2017 Update

Please see below some photo updates on Salisbury. We have been advised that construction is currently expected for an April completion.

SalisburyFeb17_2

SalisburyFeb17_6
SalisburyFeb17_4 SalisburyFeb17_3 SalisburyFeb17_1

Read more

28 Salisbury Street – December 2016 Update

Construction is progressing well and is now at lock up stage.

Plastering and external cladding are in progress with tiling aiming to be completed before Christmas.

We expect the project will be settling end of February/early March 2017.

salisbury_dec2016 salisbury_dec2016_2 salisbury_dec2016_3

Read more

28 Salisbury Street – October 2016 Update

The project is at lock-up stage.

Internal plastering has begun and will be followed by tiling and bathrooms.

Aiming for approximately mid-December Settlements, pending weather.

img_3002img_2997

Read more

28 Salisbury Street – September 2016 Update

Lock-up targeting the 1st of October.

Aiming for competition in approximately mid December.

img_2808 img_2809 img_2810 img_2811

Read more

28 Salisbury Street – August 2016 Update

Roofing should be completed this week. Windows and doors installed next week. Lock-up will be completed within the next 2-3 weeks. Then joinery will follow. 

IMG_9283 IMG_9282 IMG_9281

Read more

28 Salisbury Street – July 2016 Update

The ground floor and first floor framing stages are complete.

Roofing members are expected to be installed by the end of this week.

Lock-up stage (installation of all external doors, windows and cladding) should be completed in the next three weeks.

IMG_7955 IMG_7956 IMG_7957 IMG_7958

 

Read more

28 Salisbury Street – May 2016 Update

1

Read more

28 Salisbury Street – April 2016 Update

The foundations and some framing are expected to be installed by the end of the month.

Photos to follow once these are in place, stay tuned.

Read more

28 Salisbury Street – March 2016 Update

Construction is underway.

Underground services and land surveying is being completed now, with slab pour scheduled for a March completion and framing going up in April.

 

Read more
Next Page »