Brunswick Heart/288 Albert – April 2017 Update

We are happy to announce the development is currently at level 4-5 for precast installation and is progressing nicely. Completion expected to be Early 2018.

Read more

Brunswick Heart/288 Albert – December 2016 Update

We wish to advise that the basement and excavation works at 288 Albert have been completed. The basement 1 slab was also poured and we are currently working on the ground floor slab.

The project is currently expected to be completed in early 2018.

From the team at Castran Gilbert, we hope you have a Happy Holiday!

Read more

Brunswick Heart – November 2016 Update

CBD Development Group were excited to celebrate the construction commencement ceremony of 288 Albert, and to announce L.U. Simon as the project builders. With the piling process already under way, the estimated construction completion date is early 2019.

To mark the occasion and to extend support to the Brunswick community, CBD Development Group’s Director Mr. Chen Guo Jing presented donations to the following local organizations:
1. CERES Community Environment Park – ceres.org.au
2. Northern Support Services – nss.org.au

The 288 Albert display suite can be accessed at 282 Albert Street, Brunswick from 10am till 6pm Monday to Sunday.

november-2016-2

november-2016

Read more

Brunswick Heart – August 2016 Update

The Developer has announced that L.U Simon have been appointed as the Builder of Brunswick Heart. They are commencing their site preparation works; Piling will commence once the site mobilisation is complete.

Read more

Brunswick Heart – June 2016 Update

Negotiations with the Developers preferred Builder is ongoing, early piling works are planned to commence imminently.

Read more

Brunswick Heart – April 2016 Update

Excavation works at Brunswick Heart have commenced with guidance of the EPA auditors to remove undesirable soils.

Building finalists have been selected and the final negotiations are taking place.

Read more

Brunswick Heart – February 2016 Update

10566533_10153220859330009_1529041104_n 12463567_10153220859505009_561177810_n 12463674_10153220859415009_821004381_n 12463808_10153220859995009_1697983778_n 12463827_10153220859470009_704368354_n 12463920_10153220860080009_658895265_n 12468003_10153220859060009_2097908608_n 12476442_10153220859205009_2085345563_n

Read more

Brunswick Heart – October 2015 Update

Demolition has commenced with building works expected to commence in December 2015.

Completion aiming for approximately early 2017.

Read more

Brunswick Heart – September 2015 Update

The Developer has engaged the demolition contractor who has lodged all of the relevant information to Moreland Council to approve the demolition process, this was done last week and is usually a 3 week period, so hopefully they will have the demolition permit in 2 more weeks.

 Demolition of the existing buildings will begin as soon as the permit is issued. 

Read more