St George – March 2017 Update

Good news!

The Occupancy Permit for St George has issued, so we expect settlements will be called in the next few days.

Arrangements for purchaser inspections are also in motion (exact dates and times to be confirmed), but most likely to be later next week (5-7 April, 2017).

Please ensure your finances are in order, settlements usually occur within 2 weeks from the official call for settlement.

Just a reminder:

The vendor’s representative for Bank Valuations is:

 Patrick Tobin
 email: patrick.tobin@tobindevelopments.com.au
 mobile: 0403 802 136

The vendor’s representative for Purchaser Inspections is:

Robert Fidanza
email: rob@kbpg.com.au
mobile: 0432 820 277

    Robert will shortly be contacting you to book a time to view your brand new apartment with your selling agent!

StGeorge_march2

Read more

St George – March 2017 Update

We have received the below updates from the developer:


Works are progressing well on site, the end is so close and the building is looking fantastic!

We are busy applying the finishing touches to the building, and the cleaners have also commenced with their preliminary clean of the building.

We anticipate settlement will occur in second half of March 2017.

Once settlements are called, purchasers will be invited to inspect the finished apartments.

The vendor’s representative for inspections is:

Robert Fidanza
email: rob@kbpg.com.au
mobile: 0432 820 277
Please drop Robert an email so he knows your most up to date contact details to arrange inspections.

For valuations please contact Patrick Tobin:

Patrick Tobin
email: patrick.tobin@tobindevelopments.com.au
mobile: 0403 802 136

Please ensure you have organised your financing to allow settlement, if you require any assistance with bank finance, please contact:

Adina Zhang
Bank of Melbourne
email: adina.zhang@bankofmelbourne.com.au
mobile: 0422 980 058

StGeorge_Feb17_6 StGeorge_Feb17_7 StGeorge_Feb17_8 StGeorge_Feb17_9

Read more

St. George – February 2017 Update

Great news! We have received the following updates for 66 St Georges Road, Northcote:

All kitchen joinery are now installed with the remaining bathroom and bedroom joinery to be installed in the next few days.
Balcony tiling is almost complete and most of the balcony balustrades have been installed.
All floor finishes (timber floorboards, carpet and tiles) have been installed in the apartments on ground levels and levels 1 and 2.  Level 3 and 4 to be completed in the next few days.
All appliances have been installed and final services fit off is almost complete on all levels.
The building lift is complete and fully operational.
The car stackers have been completed and are fully operational.

Remaining works are expected to be finished in about two weeks near the start of March and settlements are estimated to be called approximately a few weeks after (Mid March)

We look forward to presenting you with an amazing finished product very soon!

StGeorge_Feb17_1

St George as viewed from St Georges Road

StGeorge_Feb17_2

View of a kitchen under construction

StGeorge_Feb17_5

Select lobby detail

StGeorge_Feb17_4

Mirrored robes are in

StGeorge_Feb17_3

Carstackers are in

Read more

St. George – December 2016 Update (Part 2)

As requested, a photo of the current exterior. Completion is due in approximately mid-February 2017. Please organise settlement and finance to be ready for this date.

stgeorge_dec_6

Read more

St. George – December 2016 Update

We have received the following updates from the developer:


Constructions at St. George is progressing well!

  • All windows and glazing installed
  • The building is now fully enclosed and the roof is on.
  • Plastering of all apartment walls and ceilings almost complete.
  • First coats of paint completed on walls and ceilings on ground floor apartments as well as levels 1 & 2.
  • Tiling of bathrooms has commenced in the ground and level 1 apartments.
  • Balustrade installation has commenced
  • Kitchen and bathroom joinery prototype had installed and inspected, joinery installation on ground floor has commenced
  • All leaf patterned precast concrete panels have been installed on the facade.
  • Works on track for completion in February 2017.

Settlement is likely to be in mid-late February 2017, therefore this would be a great time to get your finance organised, should you require finance for settlement.

We have worked very successfully with a financier at the Bank of Melbourne on past projects,and  she has assisted many purchasers to obtain competitive finance rates and terms. Her contact details are enclosed – we would encourage purchasers to get in touch with her if you would like any assistance with obtaining finance.

Adina Zhang
Lending Manager, Bank of Melbourne
Phone: (03) 8804 5300
Mobile: 0422 980 058
Email: adina.zhang@bankofmelbourne.com.au

Some picture of progress on site have been enclosed below:

Interior plastering and painting on schedulestgeorge_dec_5

Tiling has commenced on site stgeorge_dec_4

Leaf windows as viewed from inside, plenty of natural light

stgeorge_dec_3

Exterior 2: leaf pattern feature at front of building  stgeorge_dec_2

Wonderful unobstructed views towards the city and park lands. stgeorge_dec_1

Read more

ST. GEORGE – October 2016 Update

Ground floor apartment walls and ceilings plastered

Ground floor painting of apartment walls commenced

Ground floor glazing almost complete

Level 1 & 2 plastering of walls underway

Level 3 services rough in underway

Level 4 roof installation almost complete

Tower crane removed and lift shaft completed

Lift installation about to commence

Joinery to be installed next week

Current estimated completion date is still the first quarter of 2017.

1Tower crane removed, lift shaft completed.2St George the life style location, bike path and tram stop at your front door.3The patterned precast panels for the balustrades are up! 4Works on the penthouse level, city and park views in the background.5Ground floor apartment progress, windows are in, fully plastered and painting has commenced.6Roughing-in well advanced on the upper levels.

Read more

ST. GEORGE – September 2016 Update

The following is a summary of the current status of the St George construction works:

– concrete structure complete
– decorative leaf precast concrete panels installed for feature wall on St George’s Road facade.
– metal roof structure installation commenced.
– wall frames and services rough-in almost complete on ground floor
-wall frames and services rough-in commenced on Level 1
– Installation of Windows in ground floor commenced.

Amazing views from level 4, this one shows uninterrupted views of the city skyline and parklands.

2

Unobstructed views to the north.

3

Pretty English country side views towards the east.

4Construction progress as viewed from St Georges Road, towards the south.

5

Rough-ins commenced internally.

6

Read more

ST. GEORGE – August 2016 Update

Formwork in basement to support concrete pours of upper levels now removed.

Insulation installed on underside of ground floor slab.

Tower crane in operation.

Level 3 floor concrete slab poured.

Level 3 columns and walls installed.

Level 4 floor concrete slab targeted .to be poured on Friday 19th August

Decorative precast concrete panels continue to be installed on the perimeter of the building.

The construction works are forecast to be completed in the 1st quarter of 2017.

Please see also a few photos of latest progress on site.

1 2 3 4

Read more

ST. GEORGE – July 2016 Update Part 2

The building structure is currently up to level 2, the floor slabs were poured this week.

Work is progressing with formwork in situ on level 2.

The first few feature precast panels were installed and looks fantastic.

Still targeting for completion in approximately late 2016 to first quarter 2017.