Canterbury Rise – Completed!

The completed Canterbury Rise development:

canterbury_988_box_hill_south_facade_high_res canterbury_988_box_hill_south_bathroom_high_res canterbury_988_box_hill_south_living_high_res

Read more

Canterbury Rise – June 2017 Update

We have been informed by the developer of 988 Canterbury Road that there have been delays at the site and hence settlement. Valuations will instead now be taking place around mid – late July and purchasers will be contacted in the coming weeks with details on how these can be arranged. We will provide a new estimated settlement date once we receive more details from the developer.

Read more

Canterbury Rise – May 2017 Update

The developer has passed on the following update for Canterbury Rise:


Our construction team is getting all Handover Material ready for purchasers at settlement. When it is time for purchaser and valuer inspections, the vendors solicitors will notify all our purchasers directly. There will be a slight delay in settlement due to the weather (we lost many days due to the rain).

Read more

Canterbury Rise – April 2017 Update

Due to weather conditions, public holidays and trades, the construction team have advised settlement will now take place in July. The Vendors solicitor will inform all the buyer in advance to get loans ready and we will give all buyers opportunity to inspect the property before settlement.

Read more

Canterbury Rise – April 2017 Update

Great news! We have been provided with the following update by the developer of Canterbury Rise:

Townhouses are partly in final stage, partly in fixing stage and the apartments are currently in cladding and fixing stage.

We will provide further updates as the project progresses.

Canterbury Rise April 2017 1 Canterbury Rise April 2017 2 Canterbury Rise April 2017 3 Canterbury Rise April 2017 34

Read more

Canterbury Rise – January 2017 Update

We have been advised that Canterbury Rise is currently at the Lock-Up stage with completion expected to be around May 2017.
The two blocks of townhouses close to the park are expected to finish earlier than the other townhouse blocks and apartments.

Canterbury Rise Jan 2017 A Canterbury Rise Jan 2017 B Canterbury Rise Jan 2017 C

Read more

Canterbury Rise – October 2016 Update

Canterbury Rise is at lockup stage at the moment, which means from now on it will move much faster.

The Developer regularly updates their social media with progress photos for Canterbury Rise, so you can now also follow up from the following:

Facebook: https://www.facebook.com/goldfieldgroup/

Linkedin: https://www.linkedin.com/company/canterbury-rise

Twitter: https://twitter.com/goldfieldgroup

Instagram: https://www.instagram.com/goldfieldgroup/

(For Chinese purchasers) Weibo: http://www.weibo.com/goldfieldgroup

14543844_316754785364512_5560168833309439916_o 14556573_316754738697850_3709696862689916969_o 14633127_316754805364510_6985571298522413379_o 14633576_316754715364519_2764657561052224543_o

Read more

Canterbury Rise – September 2016 Update

img_7101_resize img_7104_resize img_7105_resize img_7106_resize img_7109_resize img_7110_resize

Read more

Canterbury Rise – August 2016 Update

IMG_6750_resize IMG_6751_resize IMG_6752_resize IMG_6753_resize IMG_6754_resize

Read more

Canterbury Rise – June 2016 Update

Please see below photos from Canterbury Rise.

The Builders are currently working on the framing and roof structures of the Townhouses (Level 2 and 3).

The Apartments are also being built. The structure of the basement is completed and they are working on the ground floor.

IMG_1498 IMG_1502 IMG_1507 IMG_1509

 

Read more