Gravity – June 2017 Update

Please find below an update from the developer of Gravity:


With Gravity almost complete, we are now ready for bank valuations. The financier may require a bank valuation inspection to be carried out in order to complete the loan application.

The bank valuation inspections are by appointment only and must be booked through us.

Please note due to occupational health and safety, no person will be granted access without being pre-registered.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       Completed
  5. Services rough in                     Completed
  6. Window glazing                        Completed
  7. Facade cladding                       Completed
  8. Internal fit out works                In progress
  9. Finishing works                        In progress
  10. Title registration                       Lodged
  11. Ready to settle

 

Access Times for Valuers

Access times available are strictly as follows by pre-registration only. We have allowed 15 minute intervals for each booking i.e. 9.00am, 9.15am, 9.30am etc:

Ground level to 16                   Monday 19 June to Wednesday 21 June         9.00am to 3.00pm
Level 17 to 28                          Monday 26 June to Wednesday 28 June         9.00am to 3.00pm

 

Pre Registration Process for Valuers 

All apartments must be pre-registered individually otherwise access will be denied.

Registration process is as follows:

  • Valuation requests must include the following information prior to being pre-registered:
  1. Valuation company name
  2. Valuation booking contact email address
  3. Valuation person
  4. Valuation person mobile phone no
  5. Valuation person email address
  6. Apartment no to be inspected
  7. Preferred valuation time option 1
  8. Preferred valuation time option 2
  • Once the request has been received, we will confirm by email the booking, or recommend an alternative time.

On site, we will induct the valuer, explain the process, provide a valuation manual, and walk the valuer through the apartment.

Please note, no access will be granted if the specific apartment is not pre-registered.

All valuers are required to arrive 5 minutes early for registration.

The meeting point for the valuers is at the entry to the site office located on Gladstone Street.

 

Settlement Date

Settlement is anticipated for early August 2017. We will keep you updated as we get closer to this date.

 

Legal Matters & Finance

For legal matters, please ensure you continue to liaise with the legal representative.

For finance matters, all applications should now be approved subject to a bank valuation if required. If there are any issues with the finance, please ensure that we are contacted immediately, as we may be able to assist.

 

Final Inspection Appointments

The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only.

Again, the final inspection will be by appointment only and must be booked through us.

We will advise you of the final inspection date with our next update.

Contact Person
Kim is your dedicated contact person for all matters relating to valuations and settlement.

Name:  Kim Velardi
Email:  kim@blueearth.com.au
Phone: 03 9347 6006

Read more

Gravity – May 2017 Update

Please find below an update on the Gravity project from the developer:


With Gravity almost complete, we are now ready for bank valuations. The financier may require a bank valuation inspection to be carried out in order to complete the loan application.

The bank valuation inspections are by appointment only and must be booked through us.

Please note due to occupational health and safety, no person will be granted access without being pre-registered.

In relation to the programme, the status is as follows:

Programme
The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       Completed
  5. Services rough in                     Completed
  6. Window glazing                        Completed
  7. Facade cladding                       Completed
  8. Internal fit out works                In progress
  9. Finishing works                        In progress
  10. Title registration                       Lodged
  11. Ready to settle

 

Access Times for Valuers
Access times available are strictly as follows by pre-registration only. We have allowed 15 minute intervals for each booking i.e. 9.00am, 9.15am, 9.30am etc:

Level 7 to 11                Monday 12 June to Wednesday 14 June         9.00am to 3.00pm
Level 12 to 28              Monday 19 June to Wednesday 21 June         9.00am to 3.00pm
Ground Level to 6        Monday 19 June to Wednesday 21 June         9.00am to 3.00pm

 

Pre Registration Process for Valuers
All apartments must be pre-registered individually otherwise access will be denied.

Registration process is as follows:

  • Valuation requests must include the following information prior to being pre-registered:
  1. Valuation company name
  2. Valuation booking contact email address
  3. Valuation person
  4. Valuation person mobile phone no
  5. Valuation person email address
  6. Apartment no to be inspected
  7. Preferred valuation time option 1
  8. Preferred valuation time option 2
  • Once the request has been received, we will confirm by email the booking, or recommend an alternative time.

On site, we will induct the valuer, explain the process, provide a valuation manual, and walk the valuer through the apartment.

Please note, no access will be granted if the specific apartment is not pre-registered.

All valuers are required to arrive 5 minutes early for registration.

The meeting point for the valuers is at the entry to the site office located on Gladstone Street.

Settlement Date
Settlement is anticipated for early July 2017.

We will keep you updated as we get closer to this date.
Legal Matters & Finance
For legal matters, please ensure you continue to liaise with the legal representative.

For finance matters, all applications should now be approved subject to a bank valuation if required. If there are any issues with the finance, please ensure that we are contacted immediately, as we may be able to assist.

Final Inspection Appointments
The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only.

Again, the final inspection will be by appointment only and must be booked through us.

We will advise you of the final inspection date with our next update.

 
Contact Person
Kim is your dedicated contact person for all matters relating to valuations and settlement.

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

We thank you for your cooperation.

Read more

Gravity – April 2017 Update

Please find below update from the developer of the Gravity development:


Gravity is progressing to programme thanks to the great work of Hamilton Marino builders.

This will be our final update prior to moving into the settlement updates phase.

Onsite, works are progressing extremely well with the majority of external building works now complete. The tower crane has now been dismantled, signalling the end of the heavy lifting. The scaffolding has been peeled off showcasing the beautiful architectural elements of the building including the architectural fins.

Internally, all the contractors are working cohesively to deliver the project to the highest standard in a timely and orderly manner. Kitchens, bathrooms, plastering and tiling are almost complete, as well as all the wonderful shared spaces including the private dining room, outdoor cinema, spa, bbq, and lounge.

Internally, the various trades including carpenters, joinery makers, electricians, plumbers and plasterers are sequentially working their way up the building. Most apartments up to level 24 have been completed.

In relation to the programme the status is as follows:

Programme

The key programme items are as follows:

 

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       In Progress
  5. Services rough in                     In Progress
  6. Window glazing                        In Progress
  7. Facade cladding                       In Progress
  8. Internal fit out works                In Progress
  9. Finishing works                        In Progress
  10. Title registration
  11. Ready to settle

 

Our next update will provide firm dates on valuations times and settlement.

Settlement Date
Settlement is anticipated for early late July 2017.
We will keep you updated as we get closer to this date.

Legal Matters

For legal matters, please ensure you continue to liaise with the legal representative. They will require a fully executed copy of the Contract of Sale as a starting point. If a legal representative is yet to be appointed, please ensure it is done so immediately.

Finance Application

If finance is required to settle the apartment, you need to ensure you are working diligently with them to ensure all documentation is in place in readiness for settlement. Please note the application process is longer, and significantly slower. If a financier is yet to be appointed, please ensure it is done so immediately.

Bank Valuation
The financier may require a bank valuation inspection to be carried out in order to complete the loan application.
The bank valuation inspections are by appointment only and must be booked through us.
In due course we will provide you will details on the valuation process.

At this stage, we expect valuations to commence in early June 2017. We will advise you of a firmer date with our next update.

Final Inspection Appointments
The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only.
Again, the final inspection will be by appointment only and must be booked through us.
We will advise you of firmer date with our next update.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:  kim@blueearth.com.au
Phone: 03 9347 6006
Gravity April 1 (1) Gravity April 2 (1) Gravity April 3 (1) Gravity April 4 (1) Gravity April 5 (1) Gravity April 6 Gravity April 7 Gravity April 8

Read more

Gravity – January 2017 Update

We have received the below updates from the developer of Gravity.


Gravity is progressing ahead of programme thanks to the great work of Hamilton Marino.

Structural works continue, with levels 28-30 to be poured by the end of February and therefore topping out the structure. Apartment internal fitouts have now commenced on level 23, and continue on the levels below this.

The tower crane is expected to be dismantled by mid-March, with all windows and external architectural fins to be completed by the end of March.

In relation to the construction programme the status is as follows:

Construction Programme

The key programme items are as follows:

Stage                                      Status

Site set up works:                    Completed

Bulk excavation:                       Completed

Basement works:                     Completed

Structure works:                      In Progress

Services rough in:                    In Progress

Window glazing:                       In Progress

Facade cladding:                      In Progress

Internal fit out works:               In Progress

Finishing works

Practical completion

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for June 2017.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Below are updated construction photos.

We thank you for your cooperation.

Gravity Jan17_I Gravity Jan17_H Gravity Jan17_G Gravity Jan17_F Gravity Jan17_E Gravity Jan17_D Gravity Jan17_C Gravity Jan17_B Gravity Jan17_A

Read more

Gravity – November 2016 Update

Gravity is progressing to programme thanks to the great work of Hamilton Marino.

The structure is on target to be completed by Christmas, with only 5 of the remaining 29 levels to be completed.

Externally, the feature works on the architectural fins have commenced. Internally, the services rough is now underway.

Construction Programme

The key programme items are as follows:

      Stage                                       Status

Site set up works:                           Completed

Retention works excavation:        Completed

Structure works:                              In Progress

Services rough in                              In Progress

Window glazing                                In Progress

Facade cladding                                In Progress

Internal fit out works                       In Progress

Finishing works

Practical completion

Settlement Date
Settlement is anticipated for June 2017.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

We attach updated construction photos of the beautiful feature fins as well as a prototype kitchen and bathroom.

gravity-photo-1 gravity-photo-2 gravity-photo-3 gravity-photo-4

Read more

Gravity – September 2016 Update

Gravity is progressing well with the structure completed to level 18. With an additional level being constructed every second week, we are on target to complete the external structure by November this year.

 Internally, the works have commenced with all the services currently being roughed in. Like the structure, the services and internal finishes commence at the base of the builder and work their way up.

Moving forward, we will provide you regular updates.

Our team have a dedicated contact person as the point of contact for all matters relating to Gravity.

Settlement Date
Settlement is anticipated for June 2017. 

We will keep you updated as we get closer to this date.


Contact Person
Jessica Hamra will be your dedicated contact person for all matters in relation to settlement. 

Her details are as follows:

Name:  Jessica Hamra

Email:   jhamra@blueearth.com.au

Phone: 03 9347 6006

We attach updated construction photos showcasing the structure progress as well as the amazing views.

gravity-photo-1 gravity-photo-2 gravity-photo-3 gravity-photo-4 gravity-photo-5 gravity-photo-6

Read more

Gravity – June 2016 Update

Gravity is progressing extremely well with the structure completed to level 9. With Hamilton Marino Builders constructing an additional level every second week, we are on target to complete the structure by November this year.

Internally, the works have commenced with all the services currently being roughed in. Like the structure, the services and internal finishes commence at the base of the builder and work their way up.

Moving forward, we will provide you regular updates.

Our team will have a dedicated contact person as the point of contact for all matters relating to Gravity.

Settlement Date
Settlement is anticipated for June 2017. 

We will keep you updated as we get closer to this date.


Contact Person
Jessica Hamra will be your dedicated contact person for all matters in relation to settlement. 

Her details are as follows:

Name:  Jessica Hamra

Email:   jhamra@blueearth.com.au

Phone: 03 9347 6006

We attach updated construction photos showcasing the structure progress as well as the amazing views.

We thank you for your cooperation.

Gravity Photo 1 Gravity Photo 2 Gravity Photo 3 Gravity Photo 4 Gravity Photo 5 Gravity Photo 6

 

Read more

Gravity – May 2016 Update

We are happy to inform you that the level 5 concrete slab is going to be poured by the end of this week and the podium slab is going to be poured by the end of next week.

IMG_3186 IMG_3185 IMG_3180

Read more

Gravity – April 2016 Update

Gravity_logo

PROGRESS UPDATE

APRIL 2016

Construction has been progressing well since the last update.

We are expecting to have the Level 2 concrete slab poured by the end of this week.

The estimated completion date for Gravity is now May 2017.

We will continue to update you on progress of the build throughout construction. If you would like to view construction updates for Gravity anytime, you may visit the 360 Property Group website here.

Change of Contact Details

As we will be sending out regular, important information from now until settlement we need to ensure we have your correct contact details. If your contact details change please notify us at skoski@360propertygroup.com.au & cgsales@castrangilbert.com.au so we may update our records accordingly.

Gravity_1 Gravity_2

Read more

Gravity – March 2016 Update

Here is the March Construction update for Gravity Tower. http://web.360propertygroup.com.au/gravity-progess-update-march

You can also access all construction updates here  

 

Read more
Next Page »