ORR – June 2017 Update

Please find below an update from the developer for the ORR apartments at 360 Orrong Road:


We’re on track for completion in August!

Windows have been installed up to level 3 with level 4 commencing next week.  Plastering mostly done and bathrooms are being tiled.  Kitchens, a critical path item, are due for delivery week beginning 19th June.  Once they’ve been installed it’s on to splashbacks, fit off, floors and final painting.

Level 4 roof structure almost complete, timber feature elements are being installed over the next couple of weeks as well as the canopies.  Lifts have arrived and are being installed.

Woolworths have started their rough-in works and will take handover at the end of the month to do their fit-out.  Permanent power is also expected to be complete by the end of the month.

We cannot provide an actual completion date as yet, it is very dependent on how long it takes Council to certify Plan of Subdivision (which is expected to be lodged in the next couple of weeks), the following bank consent requirements and then of course Land Titles Office.

Best Regards,
The ORR Team.

Read more

ORR – March 2017 Update

Please find below a construction update from the developer for the Orr development at 360 Orrong Road, Caulfield.

Orr – March 2017 Update

Read more

ORR – January 2017 Update

We are happy to advise that we have received the following updates from the developer of 360 Orrong Road.


Mother Nature has certainly thrown us a few curve balls over the past few months but ORR will start rising out of the ground over the next couple of weeks.

The ORR team will start providing regular updates going forward but just letting you know completion/settlement will be approx. mid August 2017.

The Woolworths “Metro” store will commence fit-out ahead of completion so it will be open and trading when you move in.

To ensure you receive all of the latest updates on the project, can you please send through the below information to updates@castrangilbert.com.au

Name
Apartment
Phone Number
Email Address
Postal Address
Investor/Owner occupier (select one)

 

Read more

ORR – October 2016 Update

img_0547 img_0548 img_0549 img_0550 img_0551img_0553 img_0554 img_0555

Read more

ORR – August 2016 Update Part 2

IMG_4276

Read more

ORR – August 2016 Update

Excavation is almost complete and the next stage is rock anchors followed by the pouring of the basement slab.

The Builders are still on programme to complete ORR in approximately June/July, 2017.

Read more

ORR – July 2016 Update

image1 image2 image3

Read more

ORR – June 2016 Update

Demolition is complete.

Construction has commenced with ground work and capping stone, digging of the basement is commencing now.

Read more

ORR – May 2016 Update

IMG_3868

Read more

ORR – April 2016 Update

Demolition complete and construction has now begun!  We anticipate the excavation and construction of the basement to take approximately 4 months after which we will be able to more accurately predict the completion of the building.

Watch this site for more updates.