Lantern – October 2017 Update

Please find below update from the developer for Lantern.


With Lantern almost complete, we are now ready for bank valuations. The financier may require a bank valuation inspection to be carried out in order to complete the loan application.

The bank valuation inspections are by appointment only and must be booked through us.

Please note due to occupational health and safety, no person will be granted access without being pre-registered.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

 

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       Completed
  5. Services rough in                     Completed
  6. Window glazing                        Completed
  7. Facade cladding                       Completed
  8. Internal fit out works                In progress
  9. Finishing works                        In progress
  10. Title registration                       Lodged
  11. Ready to settle

 

Access Times for Valuers

Access times available are strictly as follows by pre-registration only. We have allowed 15 minute intervals for each booking i.e. 9.00am, 9.15am, 9.30am etc:

Ground level                            Mon 30 October                                              9.00am to 2.00pm

Level 1 to level 9                     Mon 23 October to Wed 25 October               9.00am to 4.30pm

 

Pre Registration Process for Valuers 

All apartments must be pre-registered individually otherwise access will be denied.

Registration process is as follows:

  • Valuation requests must include the following information prior to being pre-registered:
  1. Valuation company name
  2. Valuation booking contact email address
  3. Valuation person
  4. Valuation person mobile phone no
  5. Valuation person email address
  6. Apartment no to be inspected
  7. Preferred valuation time option 1
  8. Preferred valuation time option 2
  • Once the request has been received, we will confirm by email the booking, or recommend an alternative time.

On site, we will induct the valuer, explain the process, provide a valuation manual, and walk the valuer through the apartment.

Please note, no access will be granted if the specific apartment is not pre-registered.

All valuers are required to arrive 5 minutes early for registration.

The meeting point and parking for the valuers is outside the site office on the ground floor.

 

Settlement Date

Settlement is anticipated for 15 November 2017.

We will keep you updated as we get closer to this date.

 

Legal Matters & Finance

For legal matters, please ensure you continue to liaise with the legal representative.

For finance matters, all applications should now be approved subject to a bank valuation if required. If there are any issues with the finance, please ensure that we are contacted immediately, as we may be able to assist.

 

Final Inspection Appointments
The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only.

Again, the final inspection will be by appointment only and must be booked through us.

We will advise you of the final inspection date with our next update.
Contact Person
Kim is your dedicated contact person for all matters relating to valuations and settlement.
Name:  Kim Velardi
Email:  kim@blueearth.com.au
Phone: 03 9347 6006

We thank you for your cooperation.

Read more

Lantern – July 2017 Update

Please find below the latest update from the developer of Lantern:


Lantern is well advanced and nearing completion. The scaffolding is currently being peeled off showcasing the beautiful architectural elements of the building. Internally, all the contractors are working cohesively to deliver the project to the highest standard in a timely and orderly manner. Kitchens, bathrooms, plastering and tiling are almost complete, as well as all the wonderful shared spaces including the green gardens, gymnasium, and roof top entertainment zones.

Moving forward, we will provide you with some helpful hints to guide you through the settlement process.
Our team have a dedicated contact person as the point of contact for all matters relating to the settlement of Lantern.
We will advise of settlement timing, assist with finance enquiries, as well as conduct bank valuation and purchaser inspections.

In relation to the programme, the status is as follows:

Programme

The key programme items are as follows:

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       Completed
  5. Services rough in                     Completed
  6. Window glazing                        Completed
  7. Facade cladding                       Completed
  8. Internal fit out works                In progress
  9. Finishing works                        In progress
  10. Title registration
  11. Ready to settle

 

Settlement Date
Settlement is anticipated for early November 2017.

We will keep you updated as we get closer to this date.

Legal Matters

For legal matters, please ensure you continue to liaise with the legal representative. They will require a fully executed copy of the Contract of Sale as a starting point. If a legal representative is yet to be appointed, please ensure it is done so immediately.

Finance Application

If finance is required to settle the apartment, you need to ensure you are working diligently with them to ensure all documentation is in place in readiness for settlement. Please note the application process is longer, and significantly slower. If a financier is yet to be appointed, please ensure it is done so immediately.

Bank Valuation
The financier may require a bank valuation inspection to be carried out in order to complete the loan application.

The bank valuation inspections are by appointment only and must be booked through us.

In due course we will provide you will details on the valuation process.

At this stage, we expect valuations to commence in early October 2017. We will advise you of a firmer date with our next update.

Final Inspection Appointments
The purchaser or a representative of the purchaser will have an opportunity to view the apartment, by appointment only.

Again, the final inspection will be by appointment only and must be booked through us.

We will advise you of firmer date with our next update.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

We attached updated construction photos showcasing the beautiful prototype apartment.

We thank you for your cooperation.

Lantern July 1 Lantern July 10 Lantern July 9 Lantern July 8 Lantern July 7 Lantern July 6 Lantern July 5 Lantern July 4 Lantern July 3 Lantern July 2

Read more

Lantern – April 2017 Update

Please find below an update from the developer of Lantern:


Lantern is continuing to progress to programme.

We have completed the basement works, and have now commenced the structure. As we work our way up the structure we will commence the cladding. The cladding will incorporate the window systems, all feature architecture elements, wall finishing, and balustrading. As the apartments become watertight, we will commence the services rough in, with internal fit out works to follows.

In relation to the programme the status is as follows:

Construction Programme

The key programme items are as follows:

 

Stage                                      Status

  1. Site set up works                     Completed
  2. Bulk excavation                        Completed
  3. Basement works                      Completed
  4. Structure works                       In progress
  5. Services rough in                     In progress
  6. Window glazing                        In progress
  7. Facade cladding                       In progress
  8. Internal fit out works
  9. Finishing works
  10. Practical completion

 

Moving forward, we will continue to provide you with regular updates.

Settlement Date
Settlement is anticipated for late 2017.

We will keep you updated as we get closer to this date.
Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

 

Name:  Kim Velardi
Email:  kim@blueearth.com.au
Phone: 03 9347 6006
 

Lantern April 1 Lantern April 2 Lantern April 3 Lantern April 4 Lantern April 5 Lantern April 6

Read more

Lantern – January 2017 Update

We have received the below updates from the developer of Lantern.


Lantern is progressing to programme thanks to great work of Orange Building Solutions.

We are currently working on completing the basement, with the full retention works now complete.  The tower crane has now been erected, in preparation for the structural. Basement level 3 slab on ground has been poured, with basement level 2 slab anticipated to be poured by the end of February.

The key dates are as follows:

Construction Commencement Date

Construction commenced in July 2016.

Construction Programme

The key programme items are as follows:

Stage                                      Status

Site set up works:                    Completed

Bulk excavation:                       Completed

Basement works:                     In progress

Structure works:

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

 

Settlement Date
Settlement is anticipated for late 2017.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi
Email:   kim@blueearth.com.au
Phone: 03 9347 6006

Below are updated construction photos.

We thank you for your cooperation.

Lantern Jan17_A Lantern Jan17_F Lantern Jan17_E Lantern Jan17_D Lantern Jan17_C Lantern Jan17_B

Read more

Lantern – November 2016 Update

Lantern is progressing to programme thanks to great work of Orange Building Solutions.

The bulk excavation is now complete with the full retention basement system now underway, with the basement targeted to be completed by the end of January.

The key dates are as follows:

Construction Commencement Date

Construction commenced in July 2016.

Construction Programme

The key programme items are as follows:

     Stage                                Status

Site set up works:                    Completed

Bulk excavation:                       Completed

Basement works:                     In Progress

Structure works:

Services rough in

Window glazing

Facade cladding

Internal fit out works

Finishing works

Practical completion

 

Settlement Date
Settlement is anticipated for late 2017.

We will keep you updated as we get closer to this date.

Contact Person
Kim is your dedicated contact person for all matters relating to construction updates and settlement.

Her details are as follows:

Name:  Kim Velardi

Email:   kim@blueearth.com.au

Phone: 03 9347 6006

We attach updated construction photos.

lantern-photo-1 lantern-photo-2

Read more

Lantern – September 2016 Update

Lantern is progressing to programme with the builder Orange Building Solutions now in possession of the site.

 The old building has now been demolished, with the bulk excavation work now underway.

We expect the full retention system and the basement to be completed by Christmas. On return from the Christmas break we will commence the structure. 

Moving forward, we will provide you with regular updates.

Our team have a dedicated contact person as the point of contact for all matters relating to Lantern.

Settlement Date
Settlement is anticipated for late 2017. 

We will keep you updated as we get closer to this date.

Contact Person
Jessica Hamra will be your dedicated contact person for all matters in relation to settlement. 

Her details are as follows: 

Name:  Jessica Hamra

Email:   jhamra@blueearth.com.au

Phone: 03 9347 6006

We attach updated construction photos.

lantern-photo-1 lantern-photo-2 lantern-photo-3 lantern-photo-4

 

Read more

Lantern – July 2016 Update

We are pleased to announce that Orange Building Solutions has been awarded the building contract at Lantern. Orange Building Solutions is a sister company to Hamilton Marino Builders, who are renowned as an industry leader in multi residential development.

This will be our 19th collaboration with Hamilton Marino Builders. Recent works completed together include the following:

Northwood Apartments in Fitzroy North

A Apartments in Brunswick East

Mink Apartments in Essendon North

On a sales front, the project has been an amazing success with 90% of apartments sold.

Moving forward, we will provide you with regular updates.

The key dates are as follows:

Construction Commencement Date

Construction commenced on 14 July 2016.

Construction Programme

The key programme items are as follows:

Site set up works

Bulk excavation

Basement works

Structure works

Service rough in

Window and facade glazing

Internal fit out works

Finishing works

Settlement Date Settlement is anticipated for Late 2017.

We will keep you updated as we get closer to this date.

Contact Person Anna Gelsumini will be your dedicated contact person for all matters in relation to settlement.

Her details are as follows:

Name:  Anna Gelsumini

Email:   anna@blueearth.com.au

Phone: 03 9347 6006

We thank you for your cooperation.

Read more

Lantern – May 2016 Update

We are pleased to announce that Orange Building Solutions has been awarded the building contract at Lantern. Orange Building Solutions is a sister company to Hamilton Marino Builders, who are renown as an industry leader in multi residential development. This would be our 16th collaboration with the Hamilton Marino Group. Recent works completed together include the following:

Northwood

A Apartments

Mink Apartments

On a sales front, the project has been an amazing success with all but ten apartments sold.

Moving forward, we will provide you with regular updates on construction and guide you through the settlement process.

At this stage we are working closely with Orange Building Solutions on the construction programme. This will include the formal start date and an estimated completion date,

Construction Commencement Date

Construction is expected to commence on 1 July 2016.

We will update you once it has formerly commenced.

Settlement Date

Settlement is anticipated for late 2017.

We will keep you updated as we get closer to this date.

Read more

Lantern – April 2016 Update

The Builders have submitted the Construction Management Plan (CMP) with the Council and are waiting their response.

The Project Manager has estimated that the construction for Lantern Apartments is expected to begin in June, 2016.

 

Read more

LANTERN – Construction Commencing

We are pleased to announce that Hamilton Marino will be commencing construction on April 1st, 2016!

Read more