Evelyn – September 2017 Update (Purchaser Inspections)

EVELYN PURCHASER INSPECTIONS
We are pleased to advise that pre-settlement inspections can now be booked in via a private 30 minute appointment.

Appointments are available at the following times:

  • Tuesday 3rd October– 9am – 1:30pm
  • Wednesday 4th  October– 9am – 1:30pm
  • Thursday 5th October – 9am – 1:30pm
  • Friday 6th October – 9am – 1:30pm
  • Saturday 7th October  – 9am – 1:30pm

 

Allocations will be made on a first in best dressed basis – please contact Rachel Sleeman on 0427 545 493 or at rsleeman@castrangilbert.com.au to book your appointment. When booking in please ensure you include your name, unit number & contact details. Each inspection to take no longer than 30 minutes.

Read more

Evelyn – September 2017 Update (Valuation Inspections)

Great News! As settlement is fastly approaching we are pleased to advise valuation inspections will be conducted from the 27th of September onwards. Please contact Dale on 0417 462 626 to arrange your inspection.

Please be reminded that this is inspection is for your bank only. We will be arranging purchaser inspections shortly and will notify all purchasers accordingly.

Read more

Evelyn – August 2017 Update (Blinds)

EVELYN – BLINDS OFFER

Good news! Due to our great relationship with George at Rolling Blinds, we have been able to pass on a discounting rate to all purchasers. All apartments have been measured and quoted, please find quote for each apartment below:

Evelyn Quote 21-08-17 1.0
Rolling Blinds Brochure 1.0

Please express your interest in by contacting George directly on the details below.

Please ensure your Name, Apartment Number and Contact Details are clearly stated.

 

George Poulios
M: 0408 700 527
george@rollingblinds.com.au
http://www.rollingblinds.com.au
Level 1 / 31 Jean Street McKinnon, 3204

We would also like to note that blinds can be measure and ordered prior to settlement, but installed only after settlement due to instructions from the developer. If for any reason you wish to contact us to discuss any details further, please do not hesitate.

Read more

Evelyn – August 2017 Update

We are pleased to advise Evelyn is progressing well and coming close to practical completion.

The crane has been removed and the lift is currently being installed. The apartments flooring and painting of the walls is on-going and works have commenced to the external paving and canopies.

The provisional completion date is the end of September 2017 or beginning of October 2017 pending, completion by the builder and how long it will take for titles to be issued.

We will be sending another update over the next 2 weeks with Valuer and Purchaser Inspection times.

Read more

Evelyn – July 2017 Update

We wish to advise that Evelyn, at 92 Maroondah Highway, Ringwood, is progressing along well. At this stage, completion is expected in 6-8 weeks. We will continue to provide further updates as the project approaches completion and settlement.

Evelyn July 1 Evelyn July 2 Evelyn July 3 Evelyn July 4 Evelyn July 5 Evelyn July 6 Evelyn July 7 Evelyn July 8

Evelyn July 9

Read more

Evelyn – April 2017 Update

Great News! We are pleased to announce the fit out of the apartments and external cladding is progressing well. Project completion planned for July 2017.

Evelyn April 1 Evelyn April 2 Evelyn April 3 Evelyn April 4 Evelyn April 5 Evelyn April 6 Evelyn April 7 Evelyn April 8 Evelyn April 9 Evelyn April 10 Evelyn April 11 Evelyn April 12 Evelyn April 13 Evelyn April 14

Read more

Evelyn – January 2017 Update

All structural works were completed prior to Christmas including the concrete roof. Fit out and services rough-in from ground floor to level four have commenced.

Evelyn is still looking to be completed by July 2017

Evelyn January 2017 A Evelyn January 2017 E Evelyn January 2017 D Evelyn January 2017 C Evelyn January 2017 B

Read more

Evelyn – October 2016 Update

The second floor concrete slab was poured on Thursday the 13th of October and the third floor slab is scheduled to be poured by the end of this month.

img_2286 img_2301 img_2315

 

Read more

Evelyn – September 2016 Update

img_1906 img_1907 img_1962

Read more

Evelyn – August 2016 Update

The ground floor slab at Evelyn is scheduled to be poured within the next month.