Evelyn – April 2017 Update

Great News! We are pleased to announce the fit out of the apartments and external cladding is progressing well. Project completion planned for July 2017.

Evelyn April 1 Evelyn April 2 Evelyn April 3 Evelyn April 4 Evelyn April 5 Evelyn April 6 Evelyn April 7 Evelyn April 8 Evelyn April 9 Evelyn April 10 Evelyn April 11 Evelyn April 12 Evelyn April 13 Evelyn April 14

Read more

Evelyn – January 2017 Update

All structural works were completed prior to Christmas including the concrete roof. Fit out and services rough-in from ground floor to level four have commenced.

Evelyn is still looking to be completed by July 2017

Evelyn January 2017 A Evelyn January 2017 E Evelyn January 2017 D Evelyn January 2017 C Evelyn January 2017 B

Read more

Evelyn – October 2016 Update

The second floor concrete slab was poured on Thursday the 13th of October and the third floor slab is scheduled to be poured by the end of this month.

img_2286 img_2301 img_2315

 

Read more

Evelyn – September 2016 Update

img_1906 img_1907 img_1962

Read more

Evelyn – August 2016 Update

The ground floor slab at Evelyn is scheduled to be poured within the next month.

IMG_1506 IMG_1508

Read more

Evelyn – July 2016 Update

Please find below site photos for 92 Maroondah Highway, Ringwood for your information.

IMG_0709 IMG_0711

Read more

Evelyn – June 2016 Update

Site Progress Photos

IMG_0301 IMG_20160603_072820

Read more

Evelyn – May 2016 Update

We are pleased to announce that construction has commenced on site at Evelyn Apartments.

Watch this space for future updates.

IMG_9978 IMG_9979

Read more

Evelyn – April 2016 Update

Great news!

The CMP has been approved by the Council for Evelyn Apartments.

The Contract has been signed with the Builder and they are scheduled to commence work next week.

Photos to follow later next week.

 

Read more

Evelyn – March 2016 Update

image2

The site has been demolished and cleared, ready for works to begin.

Read more