ORR – June 2017 Update

Please find below an update from the developer for the ORR apartments at 360 Orrong Road:


We’re on track for completion in August!

Windows have been installed up to level 3 with level 4 commencing next week.  Plastering mostly done and bathrooms are being tiled.  Kitchens, a critical path item, are due for delivery week beginning 19th June.  Once they’ve been installed it’s on to splashbacks, fit off, floors and final painting.

Level 4 roof structure almost complete, timber feature elements are being installed over the next couple of weeks as well as the canopies.  Lifts have arrived and are being installed.

Woolworths have started their rough-in works and will take handover at the end of the month to do their fit-out.  Permanent power is also expected to be complete by the end of the month.

We cannot provide an actual completion date as yet, it is very dependent on how long it takes Council to certify Plan of Subdivision (which is expected to be lodged in the next couple of weeks), the following bank consent requirements and then of course Land Titles Office.

Best Regards,
The ORR Team.