1 St Georges – October 2017 Update

Please find below latest update from the developer of 1 St Georges Avenue, Bentleigh East:


We have experienced some delays beyond our control in starting the development at 1 St Georges Avenue, Bentleigh East. The Melbourne Fire Brigade has instructed us, contrary to the Fire Engineers advice, to install sprinklers throughout the development in each apartment which has meant a redesign and resubmission for approval. We are also waiting on approval from the developer adjacent for the sewer tap in on their easement to finalise the design.

Estimated start date is now towards the end of the year. These items as you can appreciate, are out of our control.

We will endeavour to keep you updated.