Auburn Grove – December 2017 Update

We wish to advise that 28 Auburn Grove has been progressing well. The status of the project is as followed:

  • External scaffold removed
  • Balustrades installed to balconies
  • Fitoff of AC to all units
  • Permanent power supply now provided to the site and all lighting installed.
  • Cleaning commenced to units.
  • External landscaping including planter boxes commenced.

We expect Certificate of Occupancy towards the end of February. Inspections will occur progressively from Ground Floor units around end of February with settlements expected the very end of Feb to early March 2018. We will keep you updated as we receive further information.